Completed Construction Project:
SR-99 Median Improvement Project |
Contract: | 08-26 |
Contractor: | Newland Entities, Inc. of Yuba City |
General Work Description: | The project involves the improvements to the SR-99 median located between Woodward Street and Sunsweet Boulevard in Yuba City. Improvements include the installation of street lights, landscaping, irrigation, storm sewer, and concrete work. Project layout. |
Potential Traffic Impacts: | Minimal impacts, construction will take place during night hours |
Construction Dates: | October 2009 - January 2010 |
Project Location Map: | For easier navigation, open the full size SR-99 Median Improvement Project map. |