Completed Construction Project:
| Groundwater Interconnect Project |
| Contract: | 09-19 |
| Contractor: | Newland Entities, Inc. of Yuba City |
| General Work Description: | The work to be done consists in general of installing approximately 646 linear feet of 8 inch diameter domestic waterline and related appurtenances, interconnecting waterlines at four different project areas, and other items of work. |
| Potential Traffic Impacts: | Minimal traffic impacts, roads will remain accessible during construction. |
| Construction Dates: | November - January 2010 |